HD Awards 2025 - Shortlist Announced
Albert Wharf

Albert Wharf

Project

Winner

Planning Application Link View map

Number/street name:
Albert Wharf, Swedish Wharf And Comley's Wharf Wandsworth Bridge Road London SW6 2TY

Address line 2:

City:
London

Postcode:
SW6 2TY

Architect:
Allies and Morrison

Architect contact number:


Developer:
Ptarmigan Land.

Planning Authority:
London Borough of Hammersmith and Fulham

Planning Reference:
2014/03250/FUL

Date of Completion:

Schedule of Accommodation:
15 x studio apartment, 47 x 1 bed, 114 x 2 bed, 49 x 3 bed, 12 x penthouse

Tenure Mix:
100% private rent

Total number of homes:


Site size (hectares):
1.45

Net Density (homes per hectare):
163

Size of principal unit (sq m):
70 - 208

Smallest Unit (sq m):
37

Largest unit (sq m):
197

No of parking spaces:
166

Scheme PDF Download



Planning History

The planning application was submitted in July 2014 and permission granted February 2015. Pre-application discussions were held with the local authority during the design development of the scheme. During these discussions the local authority realised the potential the project had to improve the visual amenity of the key river front site. However, even though they understood the economical drive behind the bulk and massing, they imposed limitations over the scale of the proposals and their relationship with the riverside setting and wider context.

The Design Process

A programme of consultation activities was undertaken throughout the pre-planning process including two public exhibitions ensuring that local residents, local businesses, local Councillors and community groups were fully informed about the development proposals and had the opportunity to engage with the design team and the client. In addition to the public exhibitions there were regular meetings with the London Borough of Hammersmith and Fulham planning officers. The advice and comments from these meetings helped the project team to evolve the bulk, massing and layout for the scheme. The scheme was also presented to the GLA with a separate presentation of the environmental issues, noise and air quality. This extensive consultation process gave the design team the opportunity to understand and incorporate stakeholders aspirations and informed the design.

Download PDF

Scheme Information

Size

  • 139

Sustainability

  • Low energy in use

Sustainability

Next